APC Accelerator™ — Module 6 Supporting Materials
APC Accelerator™ — Module 6 Supporting Materials

Contract Practice — Level 3

NEC/JCT Reference Guide  Â·  Answer Builders  Â·  Question Bank
Knight Khonje FRICS  |  Knight Khonje APC Advisory
Module 6 Supporting Materials
Contract Practice  Â·  Level 3  Â·  Two Coaching Sessions
Lessons 6.1 & 6.2 · Reference Guide
NEC / JCT Contrast Reference Guide
A working reference for assessment preparation. Study the contrast table and the depth knowledge sections before your coaching sessions. Return to this guide when preparing answers to the question bank.

Core Philosophical Contrast

The single most important contrast — know this fluently

NEC is collaborative and proactive. It is built around early communication, joint risk management, and contemporaneous resolution. Mechanisms such as early warnings, the Accepted Programme, and the compensation event process are designed to surface and resolve issues in real time. A party that fails to use the mechanisms correctly loses protections the contract would otherwise have given them.

JCT is adversarial and reactive by comparison. It allocates risk clearly between parties and provides mechanisms for resolving disputes arising from events. There is no equivalent to the NEC collaborative management ethos built into the contract. The professional adviser's role under JCT is to ensure the client's position is protected by timely notice, accurate records, and correct use of the contractual machinery when issues arise.

Key Mechanisms — Contrast Table

Area NEC3 / NEC4 JCT (SBC / D&B / ICD)
Change / Variation mechanism Compensation Event (CE). Triggered by a defined list of events. Contractor notifies within 8 weeks of becoming aware (NEC4). PM may also notify. Assessed prospectively on Defined Cost forecast. Architect's / Contract Administrator's Instruction (AI/CAI). Valuation under Schedule 2 or at contract rates. Assessed retrospectively on actual cost or agreed rates. No strict notification deadline equivalent to NEC CE.
Time entitlement Extension of time assessed as part of the CE — time and money assessed together in a single quotation. Programme impact is a CE assessment component. Extension of Time (EoT) assessed separately from loss and expense. Relevant Events give time only. Loss and Expense is a separate application process. Architect must review EoT periodically.
Cost recovery for delay Within the CE assessment — Defined Cost of prolongation included in the quotation or PM's own assessment. No separate loss and expense application. Loss and Expense — separate application required. Contractor must give notice and provide information. Must demonstrate actual direct loss, not estimate. "Ascertain" carries specific legal weight.
Programme obligations Accepted Programme is central — contractually significant. Contractor must maintain and resubmit. Failure to maintain limits CE entitlement assessments and signals contractor default. PM must accept or reject with reasons. Master Programme required but not contractually central in the same way. Programme is evidence for EoT and loss and expense but not a mechanism in its own right.
Risk management Early Warning Register — proactive, collaborative. Both parties can add risks. Risk Reduction Meetings. Failure to give early warning may reduce CE entitlement. No equivalent early warning mechanism in standard JCT. Risk is managed through professional advice, records, and timely notices rather than a contractual risk register.
Payment Assessed amount (PWDD) certified by PM. Pay Less Notice required within prescribed period if disputing. Final date for payment is fixed by contract data. Interim Application → Interim Certificate → Pay Less Notice window → Final date for payment. Pay Less Notice failure means the notified sum is payable. Housing Grants Act provisions apply to both.
Termination Core clause 90–92. Grounds include contractor insolvency, persistent default, corruption. Amounts due on termination calculated under the applicable option. Clear process. Section 8. Employer and contractor termination provisions. Grounds differ — default, insolvency, specified events. Financial consequences differ between employer and contractor termination. Wrongful termination carries significant risk.
Dispute resolution Adjudication under W1 or W2. Senior Representatives meeting required first under Option W2. Arbitration if specified. Tribunal clause determines final forum. Adjudication (statutory right under HGCRA 1996). Mediation encouraged. Arbitration or litigation as specified. No pre-condition of senior representative meeting.
Design liability Contractor design liability defined by Works Information / Scope. Contractor takes reasonable skill and care unless fitness for purpose specified. SBC — employer carries design through consultants. D&B — contractor takes on design through Employer's Requirements and Contractor's Proposals. ICD — Contractor's Designed Portion provisions define the split. Fitness for purpose risk in D&B unless excluded.

NEC — Depth Knowledge for Level 3

Compensation Event Assessment — What Level 3 Requires
Most frequently probed NEC area

The mechanism: Under NEC4, compensation events are assessed as the effect on Defined Cost plus the Fee. A quotation submitted by the contractor uses forecast Defined Cost. The PM may instruct their own assessment if the contractor fails to submit or if the quotation is not accepted.

What assessors test: Do you understand the difference between Defined Cost and cost in the conventional sense? Can you identify when a contractor's quotation includes costs that are not Defined Cost? Do you know the deemed acceptance consequence (clause 62.6) and how to advise a client to prevent it? Do you understand the difference between an NEC4 quotation and an NEC3 quotation in terms of assessment methodology?

The Level 3 answer: Goes beyond describing the CE process to explain how you assess a CE quotation, what you look for, how you handle a contractor who inflates Defined Cost, and how you advise a client on the consequences of the process not being followed correctly.

The Accepted Programme — Commercial Significance
Most misunderstood NEC mechanism at Level 3

What it is: The latest programme accepted by the PM. Under NEC, the Accepted Programme is the contractual baseline — it is the document against which delay and disruption are assessed and CE impacts are calculated.

Why it matters commercially: If the contractor fails to maintain and submit revised programmes, their CE assessments have no reliable baseline to work from. If the PM fails to accept or reject programmes within the contractual period (2 weeks under NEC4), the submitted programme may be treated as accepted. A project with a poorly maintained Accepted Programme is a project where CE disputes are harder to resolve.

Professional advice: At project outset, advise the client to establish a programme compliance protocol — requiring the contractor to submit revised programmes at agreed intervals and ensuring the PM's responses are timely. At dispute stage, advise on the weight the Accepted Programme carries in assessing CE claims and the implications of a programme record that does not reflect what actually happened on site.

Disallowed Cost — Options C and E
Specialist area — separates experienced candidates

What it is: Under NEC Options C and E, the client pays the contractor's Defined Cost plus Fee — but not all costs the contractor incurs are Defined Cost. Disallowed Cost is the category of costs that cannot be included in Defined Cost and therefore cannot be recovered by the contractor.

Disallowed Cost includes: Costs not justified by records, costs the contractor incurred due to their own default (such as correcting defects), costs for resources not used to provide the Works, and costs resulting from failures to give early warning.

Professional advice context: On a target cost contract, identifying and disallowing cost that should not be included is a professional responsibility. An adviser who simply accepts the contractor's Defined Cost build-up without scrutiny is not protecting the client. The Level 3 answer demonstrates that you understand what can be disallowed, how you identify it in the contractor's records, and how you advise the client to raise and substantiate a disallowance formally.

JCT — Depth Knowledge for Level 3

Loss and Expense — Ascertainment
Most frequently probed JCT area

The mechanism: Under JCT, a contractor suffering loss and expense from specified matters (Relevant Matters) may make a written application. The Architect or Contract Administrator must ascertain — or instruct the Quantity Surveyor to ascertain — the amount of loss and expense. "Ascertain" means to find out with certainty — it requires actual loss to be established, not estimated.

What assessors test: Do you understand the distinction between ascertainment and estimation? Do you know the Relevant Matters that trigger entitlement? Can you explain how you would assess a loss and expense application in practice — what information you require, how you verify it, how you handle a claim that is largely unsubstantiated?

Common heads of claim: Prolongation costs (site preliminaries during extended period), financing charges, head office overheads (often assessed using the Emden or Hudson formulae), and loss of productivity (disruption). Each requires different evidence and a different assessment methodology.

The Level 3 answer: Describes your actual approach to ascertaining loss and expense — what you ask for, how you verify it, how you deal with a contractor whose application is formulaic rather than evidence-based, and how you advise the client on their liability.

JCT ICD — Contractor's Designed Portion
Specific to your Manchester City Council project

What it is: The JCT Intermediate Building Contract with Contractor's Design (ICD) is used where the employer wishes to retain design responsibility for the majority of the project but transfer specific design elements to the contractor. The CDP Provisions in Section 2 govern the contractor's design obligation for the Contractor's Designed Portion.

Design liability: The contractor is liable for the CDP to the standard of reasonable skill and care unless a fitness for purpose obligation has been expressly included. The CDP must be identified clearly — typically through the Employer's Requirements and Contractor's Proposals documents.

Relevance to your project: In a lift installation project, the lift system itself is likely to fall within a Contractor's Designed Portion. The interface between the contractor's design obligations for the lift system and the employer's design obligations for the building structure and safety systems is a professional judgement question — particularly in the context of Building Safety Regulator requirements where design responsibility and compliance are closely linked.

Professional advice: At procurement, advise the client to define the CDP scope precisely and ensure the Employer's Requirements clearly set out the performance specification and compliance standards the contractor must meet. At the dispute or claim stage, advise on whether a specific issue falls within the contractor's CDP design liability or within the employer's retained design responsibilities.

Pay-Less Notices — Protecting the Client's Position
High-stakes payment mechanism — assessors probe the consequences

The mechanism: Under JCT (and required by the Housing Grants, Construction and Regeneration Act 1996), if the employer wishes to pay less than the sum notified by the contractor in their application (or certified by the CA), a Pay-Less Notice must be issued by the prescribed date — typically 5 days before the final date for payment. The notice must specify the sum the employer considers due and the basis on which that sum is calculated.

The consequence of missing the deadline: If no Pay-Less Notice is issued in time, the employer must pay the notified sum in full by the final date for payment. Failure to do so gives the contractor the right to suspend performance under section 112 of the HGCRA. The employer cannot subsequently withhold the amount — they would need to recover it through adjudication or other proceedings.

Professional advice: Advise clients to implement a payment review calendar that sits inside the Pay-Less Notice deadline for every interim application. Ensure the Contract Administrator's valuation programme aligns with this calendar. If an application is received that the client disputes, ensure the Pay-Less Notice is issued before advising on the quantum of the dispute — protecting the client's right to withhold is the priority; the quantum argument comes second.

Lessons 6.1 & 6.2 · Answer Builders
Contract Practice Answer Builders
Complete one answer builder per session. Upload when booking via the Lesson 6.3 Calendly intake form.
Session 1 Answer Builder
NEC Contract Practice — Your Strongest Example
Session 1 scope

Choose an NEC example that involves a specific contractual mechanism — compensation event, early warning, programme management, or Disallowed Cost — where you gave professional advice that went beyond routine administration. The AMEY change management role or the NEC3 Option C highways renewal programme are strong vehicles.

Opening Answer — READY Structure

R
Recognise the Problem
What NEC contractual issue did you identify? Be specific about the mechanism — CE, early warning, programme, Disallowed Cost, deemed acceptance risk — and what you recognised.
Name the NEC version (NEC3 or NEC4), the main option, and the project context in one sentence.
E
Evaluate the Options
What contractual options were available to the client? What were the risks of each? Why was your recommended approach the most defensible?
A
Advise the Client
What specific contractual advice did you give? What document or action did you prepare or recommend? Reference the relevant NEC clause if you can do so accurately.
Clause references demonstrate depth of knowledge. If you are uncertain about a clause number, note it here and verify before the session — do not guess in the interview.
D
Deliver the Outcome
What changed? Commercial saving, programme protection, dispute avoided, CE settled at assessed value?
Y
Your Professional Responsibility
Why did the client need your professional expertise on this contractual matter? What could they not have resolved without you?
Anticipated Follow-Up Questions
Depth Probe — Contractual Mechanism
Write the specific clause-level question an assessor is likely to ask based on your opening answer.
e.g. "You mentioned the deemed acceptance provision — what is the exact process under NEC4 clause 62.6 and at what point does it trigger?"
Your answer — include clause reference if applicable…
Alternative Challenge — NEC Version or Option
How would your approach have differed under a different NEC version or main option?
e.g. "How would this situation have been handled differently under NEC3 compared to NEC4?"
Your answer…
Principle Extraction
What is your general approach to [the mechanism your example involves]?
e.g. "What is your approach to assessing compensation event quotations on NEC projects generally?"
Your answer — demonstrate a structured professional method, not a case-by-case approach…
Ambiguity Test
Write an ambiguous NEC question related to your example where the contractual answer is not straightforward.
e.g. "What is your advice when a contractor notifies a compensation event after the 8-week notification period but argues they were not aware of it until recently?"
Your answer — acknowledge the ambiguity, identify the arguments on each side, and give a professional recommendation…
Session readiness check Can you name the NEC clause number for the key mechanism in your example? Can you explain what the contractual consequence would have been if your advice had not been given? Can you describe how the NEC mechanism would work differently under a different main option? If yes to all three, you are ready for Session 1.
Session 2 Answer Builder
JCT Contract Practice — ICD / Delay & Loss and Expense
Session 2 scope

The Manchester City Council lift installation project under JCT ICD is the recommended vehicle. The Building Safety Regulator delay, the CDP provisions, and the commercial management of the delay costs give you technically rich material that most candidates cannot match. Prepare to present the ICD specifically — not JCT generically.

Opening Answer — READY Structure

R
Recognise the Problem
What JCT contractual issue arose on the project? Be specific about the mechanism — EoT, loss and expense, CDP obligations, payment, termination — and the professional challenge you identified.
Name the contract form (JCT ICD), the project type, and the contractual context in one sentence. The specificity of the ICD — and the Building Safety Act dimension — is your differentiator.
E
Evaluate the Options
What were the client's contractual options? What were the risks of accepting, challenging, or settling the contractor's position? What did your professional assessment of those options identify?
A
Advise the Client
What specific JCT-based advice did you give? What was your professional recommendation and rationale? Reference the contract mechanism (EoT clause, loss and expense provisions, CDP provisions) accurately.
D
Deliver the Outcome
What was the commercial or contractual outcome of your advice?
Y
Your Professional Responsibility
What was your specific professional contribution to the contractual resolution of this situation?
Anticipated Follow-Up Questions
Key Comparison Question — prepare this specifically
"What is the contractual mechanism for recovering delay costs under the JCT ICD, and how does it differ from the equivalent mechanism under NEC4?"
Your answer — this question will almost certainly be asked. Cover: EoT as the time mechanism under JCT (vs CE under NEC), loss and expense as the cost mechanism (vs CE cost assessment under NEC), the ascertainment requirement under JCT (vs Defined Cost assessment under NEC), and why the client's position is managed differently under each…
Depth Probe — CDP Provisions
"In a lift installation project where the contractor has design responsibility for the lift system, how do you advise a client when a Building Safety Regulator requirement creates an interface between the contractor's CDP obligations and the employer's retained design responsibilities?"
Your answer — draw on your direct project experience…
Loss and Expense Ascertainment
"How did you ascertain the contractor's loss and expense entitlement arising from the delay? What evidence did you require?"
Your answer — describe the heads of claim, the evidence you required for each, and how you handled any elements that were not adequately substantiated…
Ambiguity Test
"The contractor argues that the Building Safety Regulator delay is a Relevant Event entitling them to both time and loss and expense. The client argues it is a Relevant Event for time only. How do you advise?"
Your answer — identify the contractual arguments on each side, assess the risk of each position, and give a professional recommendation…
Session readiness check Can you explain the JCT EoT mechanism and the loss and expense provisions accurately without referring to notes? Can you describe the CDP provisions in the ICD and explain their relevance to the Building Safety Act compliance issue? Can you answer the NEC vs JCT comparison question fluently? If yes to all three, you are ready for Session 2.
Reference · Contract Practice Question Bank
Assessor Question Bank — 40 Questions
Drawn from real APC assessment panels. Use to identify your highest-risk questions and prepare structured notes. Do not attempt scripted answers for every question.
NEC — Compensation Events
1.
What is a compensation event under NEC4 and what distinguishes it from a JCT variation?
2.
Walk me through the NEC4 compensation event process from notification to implementation.
3.
What happens if the contractor fails to notify a compensation event within 8 weeks of becoming aware of it?
4.
Under NEC4, when would you instruct your own assessment of a compensation event rather than accepting the contractor's quotation?
5.
What is Defined Cost and how does it differ from cost in the conventional sense?
6.
Explain the deemed acceptance provision under NEC4 clause 62.6 and how you advise clients to prevent it arising.
7.
How does the assessment of a compensation event differ between NEC3 and NEC4?
NEC — Programme, Early Warnings, and Risk
8.
What is the commercial significance of the Accepted Programme under NEC?
9.
What are the consequences for a contractor who fails to maintain and resubmit their programme as required?
10.
What is the purpose of the early warning mechanism and how does failure to give an early warning affect a party's entitlement?
11.
Describe a situation where you used the early warning mechanism proactively. What was the outcome?
12.
How do you advise a client to respond to a contractor early warning that suggests significant additional cost?
NEC — Options and Disallowed Cost
13.
What are the commercial implications for the employer of choosing NEC4 Option C over Option A?
14.
What is Disallowed Cost under NEC Options C and E and when would you advise a client to formally disallow costs?
15.
How do you audit a contractor's Defined Cost records on an Option C contract?
16.
What is the Target Cost under NEC Option C and how is the pain/gain share mechanism calculated?
JCT — Extensions of Time and Loss and Expense
17.
What is the difference between a Relevant Event and a Relevant Matter under JCT, and why does the distinction matter?
18.
What does "ascertain" mean in the context of JCT loss and expense, and how does it differ from estimation?
19.
What heads of claim would you expect in a loss and expense application and what evidence do you require for each?
20.
How do you handle a contractor's loss and expense application that relies on the Emden or Hudson formula for head office overheads?
21.
What is the Architect's obligation in reviewing extension of time applications under JCT SBC?
22.
How does the approach to concurrent delay differ between NEC and JCT?
JCT — Design and Build / ICD
23.
How does the risk allocation under JCT Design and Build differ from JCT Standard Building Contract?
24.
What is the Contractor's Designed Portion and how is design liability allocated under the JCT ICD?
25.
What is fitness for purpose and when does it apply under JCT Design and Build?
26.
How do Employer's Requirements and Contractor's Proposals interact in a JCT D&B dispute about design scope?
JCT — Payment Provisions
27.
Explain the JCT payment mechanism including the role of the Pay-Less Notice.
28.
What is the consequence of an employer failing to issue a Pay-Less Notice before the prescribed deadline?
29.
What rights does a contractor have if an employer fails to pay the sum certified by the final date for payment?
30.
How do the HGCRA 1996 payment provisions interact with the JCT Standard Form?
Termination
31.
On what grounds can an employer terminate the contractor's employment under JCT SBC?
32.
What is the financial consequence of employer termination under JCT and how do you advise a client on the cost exposure?
33.
At what point would you advise a client to consider termination and what are the risks of wrongful termination?
34.
How does termination under NEC differ from termination under JCT in terms of process and financial consequences?
Cross-Contract and Professional Judgement
35.
What is the fundamental philosophical difference between NEC and JCT and how does it affect the professional advice you give?
36.
If a client asked you to advise on which contract form to use for a ÂŁ10 million building project, what would you recommend and why?
37.
Describe a situation where you identified a contractual risk that the client had not recognised. What was your advice?
38.
Have you ever had to advise a client that their contractual position was weaker than they believed? How did you approach that conversation?
39.
What is your approach when a contractual question arises that you are not certain about? How do you advise the client in that situation?
40.
In your experience, what is the most common cause of contractual disputes on construction projects and how do you advise clients to prevent them?